This can help streamline WO scheduling. Could be a global application in the Work Order Types. Would be very helpful to make more granular adjustments to durations at the floor plan level. Example: of potential functionality - defining Plumbing Rough by Default is a 2 day duration in the WO Types data base. Applied to all projects except if there is a further definition on the floor plan. The Holly, is a 3000sqft plan and takes more time to complete. Being able to define 3 day Plumbing Rough duration will help me plan and execute projects with proper time frames.
This idea is not planned right now, but we see potential value and may revisit it in the future.