auto schedule additional work orders based off what is initially scheduled

We would like to auto schedule Rough QC's one week in advance to the Rough work order. Is there any way to make the Rough work order trigger the Rough QC one week in advance?

  • Attach files
  • Admin
    Jordan Douthit
    Apr 6, 2026

    Hi Andrew, this is actually possible today!

    You can set this up using Scheduling Rules within the Work Order Types configuration; just use a negative number to schedule the Rough QC before the Rough work order. (i.e. -5 for one week, as weekends are not included).

    Please note that managing these rules is permissions-based, so you may need an admin to handle the initial setup.